Project details

HORSESHOE RESORT – SWITCHGEAR REPLACEMENT
Verona was engaged by Loring engineering consultants to replace the power distribution equipment at Horseshoe Resort, which had reached the end of its useful life. The project required extension planning due to long lead times and specialized equipment. The project had a short, critical shutdown window of 72 hours. The project was completed successfully and on time for the start of the busy ski season.